A turnaround is a planned shutdown of a process unit, or a whole facility, so maintenance, inspection, repair and modifications can be done with less disruption. It is also called an outage or a shutdown depending on location. It is scheduled long in advance, can last weeks, and puts many of contractors on site at once.
Key Points
- With the unit down, the safety instrumented functions (SIFs) are usually bypassed or idle, so unless a SIF was designed for that mode, the safety instrumented system (SIS) protects no one doing the work. Isolation and work permits do.
- IEC 61511 requires the hazard and risk assessment (H&RA) to consider startup, shutdown and maintenance modes, not just normal operation, so a turnaround should not be a blind spot in your study.
- A turnaround is the biggest bypass event of the year, and restart is the handover: bypasses come out, proof tests and repairs are confirmed, and any modification goes through management of change and validation first.
Example
A refinery takes its hydrocracking unit down for a four-week turnaround to open and repair heat exchangers. The SIFs are bypassed in the SIS under authorized, logged bypasses, and crews open equipment only after it is blinded, drained, purged and gas tested. Before startup, the FuSa engineer checks that every bypass is cleared, the proof tests scheduled for the outage are done and recorded, and any SIF change went through management of change.
See Also: bypass, proof test, H&RA, PSSR
Cited Sources
- IEC 61511-1:2016, Clause 8.2.1
- UK Health and Safety Executive (HSE), Guidance on permit-to-work systems (HSG250)